12 Buildings Repaired Before Bank Inspection
12 buildings repaired in 3 days after the original vendor canceled. Two days ahead of inspection. 12% under budget.
12 buildings repaired in 3 days
Project Overview
The Challenge
After a storm, multiple buildings had significant exterior damage including missing or damaged gutters, downspouts, and fascia boards. A bank inspection was scheduled within days, and the original vendor canceled at the last minute. The property needed immediate repairs across 12 buildings under extreme time constraints.
CPS Approach
- Rapid assessment and scope confirmation
- Immediate material procurement
- Deployment of two coordinated teams
- Flexible problem-solving to maintain progress
Execution
- Replacement and repair of fascia boards
- Installation and correction of gutters and downspouts
- Use of white materials with custom color matching
- Full weekend execution (Friday–Sunday)
- Concurrent work across multiple buildings
Results
- 12 buildings repaired within 3 days
- Completed 2 days ahead of inspection
- Delivered 12% under budget
- Provided client confidence and avoided inspection risk