Case Study
Multi-Property Unit Turns: 40 Units in 21 Days
40 unit turns. 3 properties. 2 cities. 21 days. Centralized planning, distributed execution, a hybrid workforce.
40 unit turns in 21 days
Project Overview
The Challenge
The client required 40 unit turns completed within a 3-week window before the holiday season. Work was distributed across three properties in two cities, with one property lacking a maintenance supervisor. Tight deadlines and coordination across multiple sites increased complexity.
CPS Approach
- Centralized planning with distributed execution
- Deployment of coordinated teams across properties
- Standardized parts and materials list creation
- Integration of internal teams and external contractors
- Parallel execution across all locations
Execution
- Interior refresh and repairs under standard turn package
- Coordination across multiple active sites
- Hybrid workforce model (internal + contractors)
- Concurrent execution across properties
Results
- 40 unit turns completed in 21 days
- Maintained consistency across properties
- Reduced coordination burden for client
- Units returned to service on schedule